HOTcoordinate with power company. per Tep good 200 amp. power kill. remove old electrical equipment and wood panel siding. Carpenter is to install new siding. power is to remain off overnight to allow for carpentry. next day install new 200 amp meter socket. 200 amp main breaker QO load center. new ground rods and bond. clearance inspection and restore power.
Permit #TC-RES-0626-03215 · tucson · issued Jun 18, 2026
$6,000
Issued
coordinate with power company. per Tep good 200 amp. power kill. remove old electrical equipment and wood panel siding. Carpenter is to install new siding. power is to remain off overnight to allow for carpentry. next day install new 200 amp meter socket. 200 amp main breaker QO load center. new ground rods and bond. clearance inspection and restore power.
1,570 sq ftVolts By Dilts LLC (Likely)