DH 224: Install 250' of drywall floor to ceiling (125' on each side) to create cooling equipment gallery.
DH 227: Install 500' of drywall floor to ceiling (250' on each side) to create cooling equipment gallery
All work to include necessary rough openings for fan wall and chilled water piping. All necessary doors and fire extinguishers indicated in the plans will also be install
Permit #PMT26-12295 · mesa · issued —
~$492,615est
Submitted
DH 224: Install 250' of drywall floor to ceiling (125' on each side) to create cooling equipment gallery. DH 227: Install 500' of drywall floor to ceiling (250' on each side) to create cooling equipment gallery All work to include necessary rough openings for fan wall and chilled water piping. All necessary doors and fire extinguishers indicated in the plans will also be install
0