Complete a recover roof project. Remove the old single ply membrane only and dispose of offsite.
Permit #TC-COM-0926-01588 · tucson · issued —
$45,613
Needs Resubmittal
Complete a recover roof project. Remove the old single ply membrane only and dispose of offsite. Then install a new 1/2" High Density Cover Board over the existing insulation in place. Fasten cover board down with the new Rhinobond plates and fasteners into grid pattern. Then install a new 80 mil S37 membrane and induction weld all plates to the membrane. Then install new flashings to walls, curbs, pipes with new 60 mil S327 sika Sarnafil membrane. Then install a new Metal Era Anchor Tite Edge metal to the perimeter edges of the building.
6,500 sq ftImperial Roof Systems Co (Likely)