The contractor is planning to install temporary portable generators on-site.
Permit #PMT26-13074 · mesa · issued —
In Review
The contractor is planning to install temporary portable generators on-site. The master plan has already been approved, under PMT24-15709 and the temporary generators will be in place for a duration of 3 to 4 months until permanent power is available. The temporary portable generators will be utilized for commissioning activities to facilitate an early start-up of all mechanical and electrical systems.